Two activities you can time separately
Kusuma and Hasibuan observed a procurement department in Indonesia. In the cycle-time column of table 2 they recorded 14.30 minutes for a request for quotation and 57.73 minutes for price comparison, or 72.03 minutes combined. Negotiation, purchase order approval and sending the order appear as separate activities. Implementation of the Lean Service to Increase Productivity in The Procurement of Goods and Services of MRO Companies, IEOM, 2022.
When should you start the clock?
In this company, comparison accounted for about four fifths of the time spent on the two activities. Speeding up only the outgoing email would leave most of the work in handling responses. Start another timer when the buyer opens the first reply. Stop when the person approving the purchase has a comparison they can use.
In technical procurement that work can include checking pack sizes, matching lines to part numbers and identifying missing quotes. Five packs of two contain the same quantity as ten individual units. The buyer must check whether the quoted price is per piece, per pack or for the batch. Count that work after automation too if the buyer still needs to verify it.
Measuring your own team
Choose several similar bills of materials. Time preparation through dispatch, pause while waiting for suppliers and resume when comparing responses. During a VendorIQ pilot, measure the same activities on lists with comparable numbers of lines, quotes and exceptions.
Record those counts for each example. A short list might take 25 minutes manually while a project order with delivery exceptions takes two hours. Calculate the difference separately for each type, then weight it by how often it actually occurs.
The calculator takes monthly RFQs and total BOM lines. For 100 RFQs and 1,000 lines, saving ten minutes per RFQ gives 1,000 minutes and two minutes per line gives another 2,000. Together that is 50 hours. Replace the example times with measurements from your team. Buyer time calculator.