Choosing an hourly rate
According to Statistics Poland, one hour worked cost employers PLN 76.82 on average in 2024. This measure divides total labour costs by actual hours worked. It covers many occupations. For your own team, use payroll costs and hours from the same period. Statistics Poland, Labour costs in 2024.
Why does the cost per paid hour differ?
In the same report, an hour paid cost PLN 66.34. Employers also pay for some time when the employee is away from procurement duties, such as annual leave. Total cost divided by hours actually worked has a smaller denominator. This makes the worked-hour rate a useful reference for time spent at a desk comparing supplier offers. Definitions and benchmarks in the labour cost report.
Calculating a team rate
Suppose the full cost of employing two people for one quarter is PLN 60,000 and they work 800 hours in total. The internal rate is PLN 75 per hour. Include the same people and the same quarter on both sides of the calculation. If a design engineer deals with technical exceptions while the buyer gathers quotes, value their hours separately when the data allow.
Five hours of buyer time at PLN 75 plus two engineering hours at PLN 110 are worth PLN 595. If the engineering check takes the same time after the change, the recoverable value is the buyer’s PLN 375.
Interpreting the result
At the Statistics Poland rate, 50 recovered hours are worth PLN 3,841. If the buyer spends them on harder-to-source items, the benefit is additional capacity within the existing team. If paid overtime falls, check the cash effect against payroll. Estimate the value of your team’s time.